The Kyiv city administration has estimated the budget of the further building of the Troeschyna-Osokorky subway line from Myloslavska Street to Livoberezhna metor station with electric depot Troeschyna at 5.847 billion UAH.
It learned this from a resolution of the Kyiv city administration, the wording of which was made available to the agency.
In this resolution, the Kyiv city state administration has endorsed a project of the building of the first line to consist of 6 metro stations from Myloslavska Street to Vatutina Avenue and the first stage of the Troeshyna depot.
The second step of the building of the subway line envisages the finish of the depot, and the third step of the project envisages construction of two more subway stations.
The budget of the building of the first stage is estimated at 3.367 billion UAH, the second stage of the project is estimated at 0.875 billion UAH, and the third stage of the project is estimated at 1.608 billion UAH.
The length of the line will be 12 kilometers, the capacity is estimated at 42 pairs of trains per hour, and the passenger flow is estimated at 43,000 passengers per hour.
The term of the building of the entire line is 113 months, including 48 months for the construction of the first stage. |